Week one: We’ll set up the scaffolding, deliver the skips and a Portaloo. Then, we’ll remove the roof section and install the steels and floor timbers. This leads us onto
We’ll put up the dormer, add felt, battens, and tiles to match your roof. The Velux windows go in, plus the client supplied windows or French doors will be installed to the rear.
In the penultimate week we’ll put In the staircase and chipboard flooring. We’ll build the stud walls. Outside, we’ll finish the flat roof, fascia’s, soffits, and guttering.
And in just four weeks, your loft room is now watertight. We’ll remove the scaffolding, skips, and Portaloo. Then, we’ll clean up the site. Now it’s time for you to contact friends and family in the trade, be those electricians, plumbers and plasterers, to enable you to finish and complete your loft and start enjoying your fabulous new living space.